How retainage is released on a Washington public project.

Retainage comes back only after every company on the job has filed, the agency has accepted the work, and three state agencies have signed off. Here is the sequence, with the law behind each step.

The release sequence

  1. Work completed

    The contract work is done.RCW 60.28.011

    Starts: 45-day window for claims against retainage

  2. Every affidavit approved

    L&I approves an Affidavit of Wages Paid from the prime and every subcontractor, at every tier. No retainage is released before then.RCW 39.12.040

  3. Acceptance

    The agency formally accepts the project.RCW 39.08.030

    Starts: 30-day window for payment-bond claims

  4. Where many projects stall. As of Sep 23, 2026, 605 Washington public projects over $1M finished work more than a year ago and have no Notice of Completion on file.L&I project data

  5. Notice of Completion

    The agency notifies Revenue, Employment Security, and L&I, and is told to do so immediately after acceptance.RCW 60.28.051DOR Notice of Completion

  6. State release certificates

    Each of the three agencies certifies that the taxes due from the contractor on the contract are paid. No retainage is paid before all three.RCW 60.28.051

  7. Retainage released

    After the claim period and the certificates, the agency pays the balance, keeping back only enough to cover claims that were filed. The law’s target is 60 days after completion.RCW 60.28.021RCW 60.28.011

Completion and acceptance are different dates unless your contract defines them as the same, so the claim windows can start on different days. Filings are public: approved Intents and Affidavits can be searched on L&I’s site.L&I filing search

Deadlines worth knowing

Each deadline runs from its own trigger. We never compute them from a single date.

EventDeadlineRuns fromSource
A contractor pays its subcontractor10 daysReceiving payment for that sub’s workRCW 39.04.250
Notice of a claim against retainage45 daysCompletion of the contract workRCW 60.28.011
Notice of a claim against the payment bond30 daysThe agency’s formal acceptanceRCW 39.08.030
Agency accepts a retainage bond a sub asked for30 daysThe request, unless the agency shows good causeRCW 60.28.011
Retainage released (target)60 daysCompletion, subject to the certificates and any claimsRCW 60.28.011

Exceptions apply. For example, federally funded transportation contracts hold no retainage, and small-works contracts can reduce or waive it. This page is information, not legal advice; your contract and your attorney have the final word.

Sources, quoted

Every legal claim on this site links to one of these. Each was opened and checked on Sep 23, 2026.